For about seven weeks this summer, it was unclear whether Gilbert Regional Park would grow at all. On July 30, 2026, the Town of Gilbert announced it would pause the park's next phase while Council reassessed it. The Town pointed to "financial pressures outside the Town's control, including recent state legislative changes that have reduced Gilbert's available revenue." By mid-September the pause was over and crews were still grading the land east of the lake.
That decision affects anyone who uses the park at Queen Creek and Higley Roads. The expansion is going ahead, but none of its new park amenities will be ready to use until summer 2028. Until then, the park you visit is the Phase 1 park, with construction next door. The closest new piece is a road and bridge, not a field or a dog park.
Phase 2 didn't stop and restart. Some work kept going while Council debated the rest. The sequence below comes from Town announcements, including its September 17 Council update, and reporting by the Arizona Republic:
You may have seen a large figure attached to the vote. The Arizona Republic's roughly $99 million covers the expansion of both Gilbert Regional Park and Desert Sky Park. It is not the cost of the Regional Park alone. Desert Sky's second phase broke ground in January. It will add five multi-use fields, an inclusive playground and splash pad, pickleball and tennis courts, and a new entrance off Power Road, and the Town expects it to open in March 2028.
The September contract for Gilbert Regional Park pays for a six-field youth softball complex and new parking and lighting. It also includes a roadway connection to the new Ocotillo Road bridge. That bridge is part of a separate Town project, which is why it will be finished long before the softball fields.
The Town lists the Ocotillo Road extension between Greenfield and Higley as 75% complete, with a construction timeline of "Summer 2024 - Fall 2026." The route crosses Queen Creek Wash and the East Maricopa Floodway. The Town says it will connect Greenfield and Higley and give drivers a new way into the park.
The project page's most recent update, dated August 27, 2026, describes a structure meant for more than cars. Crews were pouring concrete between the Regional Park Drive intersection and the Regional Park bridge, and from there to the Queen Creek bridge. They were also installing "decorative lighting, shade structures, and hand railing on the Park Bridge." Because the concrete pours are so large, they happen in the very early morning. If you've heard heavy equipment before sunrise, that's likely the reason.
No exact opening date has been announced. Questions go to the project hotline at 480-898-4090.
Phase 2 covers 90 more acres. Plans call for sports fields, a dog park, a skate park, a pump track, shaded event spaces and trails. The Town's FAQ also lists more playgrounds, a bike park and disc golf. Construction is scheduled for "Summer 2026 - Summer 2028," and the Town expects Phase 2 to open "by Summer 2028."
The Town says impacts on access and operations will be kept to a minimum and planned in advance. Through 2028, everything you can use is on the Phase 1 side, and from late October through the holidays most of it centers on the water.
Gilbert Regional Park Pond is one of the waters in the Arizona Game and Fish Department's Community Fishing Program. The Town describes the lake as stocked for recreational fishing, with an urban fishing pier. AZGFD's stocking schedule was revised September 30, 2026. It moves the lake from catfish to trout as the weather cools, so the dates below are the ones to plan around this season:
| Date | What's happening | Detail to know |
|---|---|---|
| Week of Oct. 26–30 | Catfish stocking | This is the last catfish week on the current schedule |
| Through Nov. 30 | The Falls splash pad, 8:30 a.m.–9:30 p.m. | Last day of the posted March 1–November 30 season |
| Nov. 27, 9 a.m.–2 p.m. start | Holiday Kickoff by Made with Love Market | The Town calendar lists Nov. 28 as the last day; the market's own schedule runs through Nov. 29 |
| Week of Dec. 7–11 | Trout stocking | First trout week of the season |
| Week of Dec. 28–Jan. 1 | Trout stocking | Second trout week, spanning the New Year holiday |
The stocking weeks are ranges, not exact days. AZGFD stocks on a random Monday through Saturday within each listed week. The schedule also warns that dates "are not guaranteed" and can change because of weather, site access, water quality or fish supply.
The trout weeks are shared across town. Discovery Ponds, McQueen Pond, Water Ranch Lake and Freestone Pond all show trout on the same two December weeks. Water Ranch Lake has special regulations, and Freestone Pond is listed as under renovation for its fall catfish weeks.
The big fall concerts are already over. Sound Bites brought Blues Traveler, Spin Doctors and local band Wyves to the event lawn on October 9. The Smoke Show, with Treaty Oak Revival and 49 Winchester, was scheduled to close the whole park from noon October 23 until 5:30 a.m. October 25. Most of the food at those events came from trucks and pop-ups. The Town describes Food Truck Alley, at the northeast edge of the event lawn, as an event-only space, so it won't have food on a regular weekday.
The park is open 5:30 a.m. to 10 p.m. Most of what the Town lists for Phase 1 is open year-round:
The splash pad's dates are less clear than the rest. The Town's amenities page calls it open 365 days a year but publishes hours only for March 1 through November 30. Call Gilbert Parks and Recreation before planning a December splash day.
Taken together, the Phase 1 park is a lake, two playgrounds, a court complex and a lawn that fills up for events. That's the park you'll be using for the next 20 months while the rest is graded, piped and lit next door.
Since the park has no daily food service, many visits will end somewhere else. About two miles north at Higley and Ray, The Mission opened at Epicenter in early 2026. Phoenix New Times reported it open by February 9, as the Latin restaurant's third Valley location. It's at 3150 E. Ray Road, Suite 180. Once the Ocotillo Road extension opens, the drive to and from the park's south side will change again. Until then, the Queen Creek Road entrance remains the way in.
At Celina Acosta we follow how projects like the Regional Park expansion and the Ocotillo Road bridge change daily life in south Gilbert. If you live near Queen Creek and Higley and want to know how two more years of construction and a new road connection might affect your home's value, request a free home valuation or schedule a consultation with our team.
Browse active listings in the area or contact us for off-market listings.
Have an expert help you find out what your home is really worth.